Build Day 144.....Plumbing Brake System #3

Pretty much completed the plumbing now. The only thing left is to make up the front flexible hoses and then I can put some fluid in and see if it all leaks or not:


Monday, March 24, 2008

Build Day 142 & 143.....Plumbing Brake System #2

Started properly with the plumbing. Over the two days I've completed the plumbing at the rear of the car plus cut the hand brake cables to length and fitted them. Also fabricated a adjustment system for the handbrake, but that's not fitted yet:


So here's how the car looks now:

Saturday, March 08, 2008

Build Day 141.....Plumbing Brake System #1

Got started properly on plumbing the brakes today. No actual pipe on yet, but all the brackets for the handbrake cable and brake lines are done. Lot's more work to do still, but progress is good.

Friday, March 07, 2008

Build Day 140.....Lot's more bits done

I've been getting the bits done I need to do before I can start plumbing up the brakes. The driverside foot panel is now in. The steering shaft has had a primer coat of paint, and I've given the exposed chassis rails a coat of underseal.